FOI 26-3115 - Document 1 OFFICIAL: Sensitive

: ve Australian Government

Department of Social Services

MINUTE Ref: EC20-000886 SECRETARY

Through:

Catherine Rule

Deputy Secretary

Disability and Carers Stream

Ce: Peter Broadhead, Group Manager, Participants and Performance

SUBJECT: Transitioning administration of the Information, Linkages and Capacity Building Program (ILC) from the National Disability Insurance Agency (NDIA) to Department of Social Services (the department)

Recommendations:

  1. That you note considerations for transition of the ILC from NDIA to the department.

NOTED / PLEASE DISCUSS

Secretary: ………….0-eee eee eee cece eee eeeeee / /2020

Issues:

The intention of ILC is to support all people with disability, not just those with individualised plans through services such as information provision, referral, community capacity building and web support. The ILC has two components:

Local Area Coordination (LAC) and grant funding. Further background is at Additional Information.

OFFICIAL: Sensitive

Page 1 of 5

Legislative and financial considerations

  1. The department is directly appropriated ILC grant funds through Program 3.2 — National Disability Insurance Scheme, and reimburses the NDIA for ILC payments made. redacted: s47C, s47E(d)

  2. redacted: s47C, s47E(d)

  3. redacted: s47C, s47E(d)

  4. redacted: s47E(d)

  5. redacted: s47E(d)

  6. redacted: s47C, s47E(d)

  7. redacted: s47C, s47E(d)

Practical considerations

  1. The ILC appropriation is approximately $130m per annum. redacted: s47E(d)

redacted: s47E(d)

  1. The Commonwealth has a contractual obligation to continue making scheduled payments under existing grant agreements. redacted: s47(O)

  2. NDIA has previously informally advised around 50 staff work on ILC grants. Most staff are based at the Geelong or Melbourne offices, one in Canberra, and three in South Australia. These staff are responsible for ILC policy, program delivery and contract management. Selection processes are undertaken by the Community Grants Hub.

  3. The management of NDIA staff and future staffing arrangements for ILC grants would need to be considered as part of any transition of this work to the department.

Stakeholder sensitivities

  1. redacted: s47C, s47E(d)

  2. redacted: s47C, s47E(d)

  3. redacted: s47C, s47E(d) The move could highlight the benefits of better connecting ILC to other related grant activities in the department, and ensuring a closer connection between the ILC and the National Disability Strategy.

Timing of transition

  1. In December 2019, the DRC agreed a review of the current ILC Investment Strategy and development of a new ILC Investment Strategy be undertaken in 2020. The new Investment Strategy is being prepared by the NDIA and is planned for release in 2021. Existing ILC grants all expire on or before 30 June 2022, with the new Investment Strategy set to guide investments beyond this point.

  2. As ILC funds to 30 June 2022 are close to being fully committed, there are two potential windows for transition:

a. In the next 2-3 months. Under this option, all existing grants and responsibility for grant rounds to commit remaining ILC funds through to July 2022 would transition quickly. This option is preferable as the department would lead the review and the development of the new Investment Strategy.

b. In June 2021 to allow the department to undertake the first selection process under the new Investment Strategy in time for implementation by July 2022. Under this option the NDIA would retain responsibility for managing existing grants through to June 2021. The NDIA would continue to lead the current review and development of the new Investment Strategy. While the department would work

FOI 26-3115 - Document 1

OFFICIAL: Sensitive

closely with the NDIA, ultimately NDIA would retain control over the future policy direction.

redacted: s47C, s47E(d)

Next Steps

  1. Should you wish to progress further with planning for transition of ILC to the department, Disability Policy Branch will develop a more detailed proposal in consultation with human resources branch; Grant Management Office; and NDIS Finance and Performance Branch.

Summary of Attachments:

redacted: s22

Financial Implications:

redacted: s47E(d)

Deregulation Impacts:

  1. There are no regulatory impacts

Consultation:

  1. Not applicable.

redacted: s47F

Flora Carapellucci Group Manager Commonwealth/State Policy 7 May 2020

OFFICIAL: Sensitive

Page 4 of 5

FOI 26-3115 - Document 1

OFFICIAL: Sensitive

Additional Information

  1. ILC was outlined conceptually in the 2011 Productivity Commission Inquiry on Disability Care and Support, originally described as Tier 2 support. The intention of ILC was to reduce or defer the entry of some people with disability into the NDIS by supporting all people with disability, not just those with individualised plans, through services such as information provision, referral, community capacity building and web support.

  2. ILC has two components: a. Local Area Coordination funded approximately $450 million per annum. This is appropriated directly to the NDIA through Program 1.2 – Community Inclusion and Capacity Development Grants and is delivered through the NDIA’s partners in the community. b. Grants to assist people with disability funded $132 million per annum. Since 2017 this is appropriated to DSS through Program 3.2 and NDIA undertake administration of the grants. DSS reimburses NDIA for grant payments made to service providers.

  3. The Disability and Carers Stream considers there are significant benefits in transitioning ILC grants to the department. These include: a. better alignment with the broader disability system and services which are the primary responsibility of the department and not the NDIA, such as Disability Employment services; disability carer reform. b. the department has significantly more experience in administering grants than the NDIA. The Community Grants Hub already run ILC assessment processes and details of ILC grants are already in FOFMS. c. the ability to increase the decision making role of Ministers in ILC selection process, including the design of programs (which is currently determined by the NDIA Board). d. and, the capability to respond more quickly, flexibly and effectively to program design concerns redacted: s47E(d). This includes adjusting funding models to reflect differences in maturity of local ILC markets, rather than adopt a one size fits all approach.

OFFICIAL: Sensitive

Page 5 of 5

General Brief

MS20-000498

To: Minister for Families and Social Services (for decision) To: Minister for the National Disability Insurance Scheme (for decision)

Subject: Transfer of the Information, Linkages and Capacity Building (ILC) grant program

Recommendations for Minister Ruston: That you

  1. Agree with Minister Robert to transfer policy and administrative responsibility for the ILC grant program from the National Disability Insurance Agency (NDIA) to the Department of Social Services (the department).

  2. Agree the transfer occur as follows:

a. The immediate transfer of policy responsibility for the future of the ILC grant program, including the lead on the evaluation of ILC grant program and development of a new Investment Strategy.

b. Transitioning approximately 300 existing ILC grants as soon as practicable, with further advice on precise arrangements and timing to be provided.

c. The department and the NDIA working closely to finalise the Individual Capacity Building grant round that closed on 6 May 2020, with further advice to be provided on how these grants will be transitioned to the department.

d. The NDIA’s two planned Economic and Community Participation grant rounds not proceed until the department provides you with further advice on options for the remaining uncommitted ILC grant funding.

  1. Agree the NDIA retain the Local Area Coordination function.

  2. If you agree recommendations 1 to 3, agree the Secretary of the department write to the Chief Executive Officer (CEO) of the NDIA to advise of your decision and the implications for the NDIA’s planned forthcoming grant rounds.

Agreed / Not Agreed Agreed / Not Agreed
Agreed / Not Agreed Agreed / Not Agreed
Agreed / Not Agreed Agreed / Not Agreed
Agreed / Not Agreed Agreed / Not Agreed
Agreed / Not Agreed Agreed / Not Agreed
Agreed / Not Agreed Agreed / Not Agreed
Agreed / Not Agreed Agreed / Not Agreed

Minister Robert’s Comments

Need to be mindful of COVID recovery imperatives.

Minister Ruston’s signature

redacted: s47F

Date: 28 / 5 / 2020