Communications and Engagement Plan Promoting end-to-end services of the Performance Management and Quality Branch

‹ PrevPage 1 of 9 · Source p. 1Next ›
Comments

DOCUMENT 20

[Image not converted to Markdown – “Document Image” – check the source PDF page for the actual content]

Communications and Engagement Plan

Promoting end-to-end services of the Performance Management and Quality Branch

Scope and strategic advice

Business objectives

  • To contribute to the sustainability of the NDIS, in line with Aspiration 6 of the Corporate Plan 2020 — 2025.
  • To support improvements to participant experience and monitor the achievement of Participant Experience Delivery (PED) KPIs under the Corporate Plan 2020 — 2025 around access, planning and participant experience by:
    • providing quality assurance
    • encouraging practice change through analysis, education and coaching
    • delivering operational and performance insights to enable business partners to identify risks and take action
  • To achieve a high-performing NDIA (and in turn improve participant experience) by promoting best practice service delivery across PED Branches and Partners in the Community (PITCs) and identifying opportunities for improvement, in line with Aspiration 5 of the Corporate Plan 2020 — 2025.
  • To uplift NDIA and PITC capabilities and maintain strong staff engagement, in line with strategic goal 5.1 of the Corporate Plan 2020 — 2025.
  • To enhance the efficiency and effectiveness of NDIA processes and systems through assurance and performance reporting, in line with strategic goal 5.2 of the

Audience analysis and risk

Agency

  • PED leadership (ELT) need to be informed and able to use PM&Q capability to monitor KPIs, PSG, adherence to SOPs, and manage emerging issues to inform senior management decisions.
  • PED Branch managers and state managers need tailored, up-to-date information to understand relevant KPIs and progress being made across PED to inform management decisions and team updates.
  • PED frontline staff need relevant, easily digestible information with clear calls to action for day-to-day work and decision-making to meet the PED KPIs and best practice service delivery.

Partners in the Community

  • Local Area Coordinators (LACs) and Early Childhood Early Intervention (ECEI) partners need relevant, timely, easily digestible information with clear calls to action for day-to-day work and decision-making to meet partner KPIs and feed into PED KPIs, supporting best practice.

Page 122 of 190

Scope and strategic advice

Corporate Plan 2020 — 2025

  • To provide PED business areas and PITCs with insights and recommendations for continuous improvement, supporting participant experience and Scheme sustainability.

2. Communications and Engagement objectives

  • To provide Agency staff and partners with guidance around the streamlined services offered by the newly restructured Performance Management and Quality (PM&Q) Branch

  • To encourage Agency staff and partners to access the services offered by the PM&Q Branch and consider PM&Q services (such as deep dives and education) in their regular ways of working

  • To promote Partners in the Community (PITCs) awareness of how PM&Q contributes to the aspirations and strategic goals of the Corporate Plan 2020 — 2025.

Audience analysis and risk

3. What is current state/future state

Current state

The PM&Q Branch has recently been restructured to include the former Quality Branch, Business Intelligence team (from the Office of the Scheme Actuary), and some Learning and Development and Change Management staff.

The effect of this restructure on PED has not yet been communicated to the business, which means that Branches across PED are not taking full advantage of the services offered by the PM&Q Branch as part of a BAU approach.

Through their assurance work, the PM&Q Branch is responsible for measuring performance for some PED KPIs and the Participant Service Improvement Plan.

9. Communications and engagement risks

  • Risk: That the development of the communications plan concurrently alongside business unit procedures causes inaccuracies or confusion

o Mitigation: That the communications plan is finalised after all relevant PM&Q procedures are finalised, prior to actioning the communication activity schedule

o Mitigation: That the communications plan receives final sign off at the SES1 level to ensure alignment with PM&Q procedures

o Mitigation: That the progress of the communications plan is added as a standing agenda item at PM&Q Branch Operations meetings

  • Risk: That staff and PITCs finds PM&Q Intranet resources

Scope and strategic advice

The Branch undertakes qualitative reviews focusing on Scheme sustainability. These ‘deep dive’ projects help internal stakeholders to understand particular issues, cohorts, or cost pressures, and provide recommendations and insights to improve systems, processes and practices.

The Branch delivers high-level insights, data and risk analysis to senior PED leadership and shares operational and performance insights to business areas across PED such as data and trend analysis, business impact, risk and recommendations — with a focus on PED KPIs, sustainability metrics and pulse metrics.

The Branch ensures operational insights cascade across PED businesses to link executive priorities to frontline activities.

Future state

PED Branches understand and access the complete, end- to-end service offered by PM&Q (as outlined in the PM&Q accountability statement), comprised of analysing data and conducting file reviews of participant plans; sharing insights; providing education and coaching; and fostering practice improvement.

The PM&Q Branch will have the visibility they need to efficiently and effectively respond to business needs and guide, educate and facilitate continuous improvement in business practices across PED Branches.

4. What does success look like?

PM&Q measurements — short-term

  • Positive feedback received from stakeholders

PM&Q measurements — long-term

  • Improved practice and adherence to SOPs across PED,

Audience analysis and risk

difficult to understand or access, which compromises success

o Mitigation: Plain English resources are presented in an audience-focused format and structure

Risk: That the communications plan causes damage to the reputation of the PM&Q Branch by only highlighting negative stories arising from reviews

o Mitigation: That key messages and content contain positive, ‘good news’ stories to highlight good practice, as well as highlighting opportunities for improvement

Risk: That PM&Q Branch processes highlighted in the communications plan cause internal confusion or disagreement during a time of change and transition for the Branch

o Mitigation: That the proposed implementation strategies are aligned throughout the Branch by PM&Q leadership

o Mitigation: That Operations Team (Branch Improvements) resources are allocated as needed to the implementation, monitoring and review of the approved communications plan

o Mitigation: That the implementation of the communications plan is added as part of the Branch performance goals and routinely monitored.

Scope and strategic advice

  • Measured through PED KPIs
  • Improved plan quality, identified through deep dive reviews, activities to satisfy the Partner Quality Framework, and end-to-end quality reviews
  • Increased proportion of team members maintaining good practice, measured through learning and development metrics, such as level 1 learning measures
  • Increased use of 360 dashboards routinely to support achievement of KPIs and focus on scheme sustainability
  • Measureable improvements are observed against PED and Participant Service Guarantee KPIs and pulse metrics, and linked to PM&Q activities and support.

Communications measurements

  • 50% increase in visits to PM&Q Intranet pages for Q3 FY21 (from Q1 FY21)
  • Engagement rates on Express staff profiles exceed benchmarks.

Audience analysis and risk

5. Key milestones

  • Communications plan is signed off at the SES1 level
  • Intranet content goes live
  • Internal communications collateral is approved
  • Communications plan is fully implemented
  • Communications plan is evaluated.

10. Feedback and evaluation process

  • Request quantitative analytics (in line with success measurements) as required
  • Request qualitative feedback from PM&Q Branch key contacts
  • Compile findings into evaluation document and coordinate approvals.

6. Key contacts

  • redacted: Senior Strategic Communications Officer, Community Engagement and Communications
  • redacted: Assistant Director of Operations (Branch

11. Approvals

  • redacted: Assistant Director of Operations (Branch Improvements), PM&Q Branch
  • Assistant Director, Community

Scope and strategic advice

Audience analysis and risk

Improvements), PM&Q Branch.

Engagement and Communications Director of Operations, PM&Q Branch

Acting Director, Community Engagement and Communications

Branch Manager, PM&Q Branch

Branch Manager, Community Engagement and Communications Branch.

Key messages

Overarching — talking about the Branch

  • The Performance Management and Quality (PM&Q) Branch empowers teams across Participant Experience Delivery (PED) and Partners in the Community (PITCs) with insights, analysis and learning and development to support delivery of a quality participant experience and a sustainable Scheme.

  • The Agency has recently combined the expertise of staff who specialise in quality assurance, business intelligence, change management and learning and development to create a complete service offering which supports a sustainable, high-performing NDIA.

  • The specialised services offered by the PM&Q Branch will give PED staff the learning and development they need to deliver their KPIs under the NDIA’s Participant Service Guarantee and Participant Service Charter.

  • Through their review and analysis work, the PM&Q Branch plays a key role in delivering a financially sustainable Scheme under the Agency’s Corporate Plan 2020 — 2025.

  • By combining their review work with a learning and development approach, and by giving you a dedicated contact point, the PM&Q Branch is working to uplift NDIA frontline capabilities while enhancing the efficiency and effectiveness of processes and systems.

Tactical — for PED Staff

  • Following a recent restructure, the Performance Management and Quality (PM&Q) Branch has been refocused to make better use of insights from our assurance activities and data analysis, before helping you embed key learnings across your wider team through learning and development.

  • NDIA staff can now access a complete, end-to-end service offering of review, analysis, insights and education from the PM&Q Branch.

  • The PM&Q Branch uses an account management model — which means you will have a single point of contact within the PM&Q Branch who will be your go-to person throughout the end-to-end process.

Page 126 of 190

Communications and Engagement Schedule

As PED staff, you can reach out to the PM&Q Branch if you:

  • Notice you’re not always hitting your team’s KPIs and want to figure out why.
  • Want to improve your team’s performance by understanding root cause impacts.
  • Come across any unforeseen cost pressures or gaps.
  • Want to help your team transition to an improved process or way of working — such as to deliver on a KPI or implement an improvement suggested during a deep dive review.

PM&Q will tailor their learning and development program to your team, to make sure you have the best chance of using key learnings to deliver a quality experience and outcomes for participants.

By accessing PM&Q’s services, you will be taking an important step toward enhancing the way you service participants.

Send a request to redacted: s22(1)(a)(ii) - irrelevant — your request will be assigned to a dedicated account manager who supports your business area.

pm&Q may also get in touch to conduct a proactive service delivery review and help you identify opportunities for process improvement.

Tactical — for PITCs

As Partners in the Community (PITCs), you play a key role in delivering a quality participant experience and the Performance Management and Quality (PM&Q) Branch will continue to support you.

As PITCs, you will still receive the review, analysis and insights services provided by the PM&Q Branch.

The PM&Q Branch will continue to review your partner plans and give you the advice and support you need to maintain good practice processes and systems.

Go live coordinator: redacted, Senior Strategic Communications Officer

Business readiness schedule

These are actions that build awareness with impacted business areas in NDIA and PITC before internal communications start.

Target audience Activity Purpose Outcome Responsibility Completion date Comments
Agency staff and PITCs Audit existing Intranet resources and Scope what needs to be done Strategic Communications and PM&Q Branch are fully aligned on the redacted: s22(1a){i) - irrelevant material November 2020 to conduct initial scoping

Activity

Target audience
Agency staff and PITCs
Purpose
Align on content scope of Intranet meeting changes updates required with
Outcome
Draft and user test content for Intranet pages Intranet resources which provide users with the information they need
Responsibility
Completion date
November 2020 to April 2021
Comments
Fully aligned oe) one

Go live with Intranet resources

| Target audience | | Agency staff and PITCs | | Purpose | | Align Intranet resources to key messages with a focus on the user | | Outcome | | High quality, user-focused resources are housed on the Intranet, aligned to communications plan | | Responsibility | | Digital Delivery team | | Completion date | | April 2021 |

Create satisfaction survey

| Target audience | | Agency staff and PITCs | | Purpose | | Allow PM&Q staff to measure satisfaction and track sentiment over time to inform PM&Q Branch decision-making following reviews | education | | Outcome | | High-quality data around business satisfaction over time with question suggestions provided by | | Responsibility | | =2@@ === | | Completion date | | April 2021 |

Update PM&Q Branch meeting

| Target audience | | PM&Q Branch | | Purpose | | Inform the Branch of supported communications plan goals and deliverables | | Outcome | | Branch is aware | | Responsibility | | = == | | Completion date | | April 2021 |

Internal communications and engagement schedule

Date Target audience (Who’s it going to?) Activity (What is it? How are you doing it?) Purpose (Why are we doing it?) Outcome (What do we expect from it?) Responsibility (Who’s doing it?) Completion date Comments
Week of 3 May 2021 Agency staff and PITCs Create a ‘good news’ case study based on a previous PM&Q review, to be housed on the PM&Q Intranet Demonstrate the value how PM&Q can help them improve their processes and performance Staff understand redacted
Week of 3 May 2021 Agency staff and PITCs Create talking points document containing key messages and a Q&A Talking points are live on the PM&Q Intranet redacted
Week of 10 May 2021 PED SES (including National Delivery, Operations and Support and Partner and Contact Centre Divisions) Send targeted email of PM&Q restructure and how to access services Inform PED SES of PM&Q restructure and how to access services PED SES are better informed of the services offered by PM&Q and how to access services written by
Week of 10 May 2021 Agency staff and PITCs Include Weekly Huddle item Inform staff of PM&Q restructure and encourage them to access services Staff are better informed of the services offered by PM&Q and how they can access services redacted Do not draft until Intranet changes are finalised
Week of 10 May 2021 Agency staff and PITCs Post Intranet notice Inform staff of PM&Q Staff are better informed of the redacted Do not draft until Intranet

8

Fol 21/22-1299

Date (When?) Target audience (Who’s it going to?) Activity (What is it? How are you doing it?) Purpose (Why are we doing it?) Outcome (What do we expect from it?) Responsibility (Who’s doing it?) Completion date (Is it done?) Comments
Week of 10 May 2021 Agency staff and PITCs Submit Express staff profile restructure and encourage them to access services services offered by PM&Q and how they can access services redacted changes are finalised

Lessons learnt

Communications

Things that worked well

Opportunities for improvement