Procurement Plan

‹ PrevPage 1 of 5 · Source p. 1Next ›
Comments

Procurement Plan

From: Acting Branch Manager, Insurance and Performance Reporting Date: 11 September 2013 Subject: Procurement of Internal Audit Services

The purpose of this minute is to seek your approval for the procurement of services in accordance with this plan to enable the selection of an internal audit provider. It is proposed to conduct the procurement as a Request for Quotation (RFQ) with KPMG, Deloitte, PwC and Ernst & Young invited to submit a response. These are considered the four providers who are able to supply the services required.

These service providers form part of the Department of Resources, Energy and Tourism Panel — Internal Audit, Risk Management, Program Evaluation, Fraud Control, Protective Security and Fraud Investigation Services — SoN 145385 which the Agency utilises.

Services and requirements

Broadly the requirement of the services is to:

  • assist the Board meet its statutory and legislative obligations by the provision of internal audit and assurance services
  • develop an internal audit plan focused on adequacy of internal controls, compliance activities and management of key business risks
  • undertake internal audit reviews in accordance with the internal audit plan and provide reports to Management and the Board on the adequacy of policies and processes
  • review and report on the integrity of financial and operational information used for annual reporting
  • identify and provide “best practice” advice on opportunities for improvement in areas reviewed
  • provide ad hoc assistance as required

Page 1 of 55

Value for Money (VFM) Assessment

Value for money will be achieved through a competitive RFQ process. The responses will be assessed against defined evaluation criteria and in accordance with a pre approved evaluation plan.

The CFO will be the approving delegate and the Branch Manager Insurance and Performance Reporting will be the contract manager.

Term of the arrangement and contract value

Services will be required between 1 November 2013 and 30 October 2014. It is anticipated that the contract value will be between $150K and $250K.

Proposed agreement type

An official order for services will be placed in accordance with panel arrangements.

Risk assessment

Existing panel being utilised to minimise service quality risks. Competitive quotation process being undertaken to minimise pricing risks.

Alternative approach

Request for Tender is alternate approach. Selection from existing panel is considered the most expedient.

Reporting

The successful provider will have clear deliverables and timelines. The contract delivery will be managed by the Branch Manager Insurance and Performance Reporting.

Consultation

Advice has been provided by the Agency’s internal Procurement team.

Conflict of Interest

Staff involved in the RFQ process will complete conflict of interest declarations as appropriate and follow standing protocols.

Recommendation

R1 - That you approve the procurement in accordance with this plan and the evaluation plan attached.

R2 — That you as the delegate approve in principle the projected expenditure of up to $250K for the full contract term.

Signed

[redacted — s22(1)(a)(ii)]

Page 2 of 55

Delegate Approval

As delegate I certify that this procurement represents best value for money and that the proposed purchase will make effective, economical and efficient use of public moneys. I have read and understand the DisabilityCare Australia Procurement Instruction and the Commonwealth Authorities and Companies Act 1997.

Under DisabilityCare Australia’ Delegations Policy, I approve this procurement plan to spend public money and there is available budget for the committed amount.

Name of the Delegate

Position Title [redacted — s22(1)(a)(ii)]

Signature: [redacted]

Date: M. . Ay. nS .

Page 3 of 55

Attachment: RFQ Evaluation Plan — Internal Audit Services

Evaluation Committee

The following team will undertake the evaluation

Position Name Branch
Chair [redacted — s22(1)(a)(ii)] Insurance and Performance Reporting
Member [redacted — s22(1)(a)(il)] Fraud and Compliance Advisor
Member [redacted]

Timetable for Evaluation

The timetable for evaluation will be as follows:

Event Timetable
Quotation requested 13 September 2013
Quotation due 11 October 2013
Board Chair advised of proposed appointment 21 October 2013
Successful provider notified 25 October 2013
Contract initiation 1 November 2013

Evaluation method

All RFQ’s will be evaluated for compliance.

A qualitative assessment method will be used to assess each RFQ against the evaluation criteria and overall value money.

Quotations will be evaluated against the following criteria:

  • Value for money;
  • Demonstrated understanding of project requirements;
  • Demonstrated skills and experience in subject matter;
  • Demonstrated capacity to meet specified timelines:
  • Demonstrated experience with similar agencies and /or insurance schemes.

A report with recommendations will be forwarded to the delegate for approval.

Unsuccessful providers will be offered the chance of a debrief after all negotiations with the successful provider have been completed.

All meetings will be minuted and reports will be maintained for audit purposes.

Each evaluation criteria will be evaluated on a 10 point scale below.

Tender Assessment Rating/Scoring Scale

Rating Scale Score
Exceptional 10
Specification requirements significantly exceeded in all areas. Claims are fully substantiated. Unequivocal support from referees. Extremely Low Risk.
Outstanding 9
Specification requirements are exceeded in most key areas & addressed to a very high standard in others. Most Claims are fully substantiated with others very well substantiated. Unequivocai support from referees. Very low risk.
Very Good 8
Specification requirements met to a very high standard in all areas. All Claims are well substantiated. Very strong support from Referees. Some manageable risks with strategies. Very Low risk.
Good 7
Specification requirements met to a high standard in all areas. Claims are well substantiated in key areas. Strong support from referee with minimal or no reservations. Low risk — all Key risks covered well.
Fair 6
Specification requirements are addressed well in all areas. Claims are well substantiated in most areas. Credible strategies that fully address all minimum requirements and exceed requirements in some areas. Some minor shortcomings. Sound referee support. Most key risks are covered well. Medium risk
Acceptable 5
Specification requirements addressed to a consistent acceptable standard with no major shortcomings. All claims are adequately substantiated. Some proposals questionable. Support from referees is adequate. Medium risk.
Marginal 4
Specification requirements not fully met and additional information/ deficiencies not adequately overcome by Tender’s clarification. Some claims unsubstantiated; others only adequate. Some proposals unworkable. Referees report adequate with minor reservations. Medium/High Risk
Poor 3
Specification requirements poorly addressed in some areas or not at all. Claims largely unsubstantiated. A number of proposals unworkable. Strong referee reservations. High risk.
Very Poor 2
Specification requirements inadequately dealt with in most or all areas. Claims almost totally unsubstantiated. A number of proposals unworkable with a high probability of service failure. Referees cannot recommend. Very High risk.
Unacceptable 1
Specification requirements not met. Claims unsubstantiated and unworkable. Significant adverse referee comments. Extreme Risk.
Non-Compliant 0
Tenderer completely failed or refused to provide a response.