Reform for outcomes program

Feedback and Working Group preferences

Proposed approach to co-design

Co-design

  • We cannot start a co-design process until we have opportunity to contribute and agree on practice guidelines.
  • Further discussion is needed on the co-design model before the group should agree to the approach for the RFO program.
  • Previous Agency attempts at co-design have been rushed. For example, by missing a meeting people have lost the opportunity to meaningfully contribute.
  • Need to acknowledge that slow and deep consideration leads to better outcomes. Deep consideration also requires transparency (an information sharing portal may work). It also requires perspectives that come from academia and research. Need to consider the latest evidence from critical policy and disability research.
  • The NDIA should ask group members what it thinks reforms could look like, rather than providing a list of proposed reforms for each initiative. (Simon Burchill)
  • There needs to be a clear definition of co-design. This process is co-production, rather than co-design, because of the predetermined parameters.
  • It should not be up to each working group what co-design means to them; rather it should be about adapting which processes will work for that group.
  • This process is not co-design but business-as-usual with the codesign label. What is happening is consultation at best, albeit with enlarged groups of consultees.
  • The Agency has not listened to what the sector believes co-design really looks like.
  • Recognition there are issues around the co-design approach taken, but it would be best to move to that working group stage and have further discussions around the co-design approach for each initiative in the working group.
  • The ‘co-design’ structure needs more consideration given to co-sensing for mental health – need to be clearer and empowering for participants and their families in asserting their own problem definition process. The NMHCCF as the DRO for Psychosocial Disability from Mental Health has specific perspectives to bring to this process from both the participant and the family /carer lived experience that is uniquely different than other disabilities represented in the NDIS.

1.2. Approach

  • Do not support an approach of working through all initiatives in a large group.
  • Very supporting of the working group approach and having a steering committee – provides an opportunity to have visibility of all working groups while not needed to be involved in all.
  • The approach we take needs to be flexible and adaptable to ensure the approach continues to operate effectively – need to reach agreement on the Outcomes framework.
  • Members of the Steering Committee should be encouraged to discuss plans for consultations and opportunities for collaboration.
  • Supports collating input/comments from members in advance of large group meetings to guide conversations.
  • Working group membership needs to be larger than 3-4 members to ensure all DRCO/IAC representatives have opportunity to participate in a working group (Slide 7 RFO Co-design approach powerpoint).
  • Working groups are divide and conquer.
  • Large groups do not achieve outcomes.
  • It’s too hard for all members of a large group to talk about all initiatives in detail.
  • Concern that giving us all a say does not deliver outcomes. There needs to be commitment to the successful delivery of improvement and timely responses to unintended consequences.
  • Working Groups should include participants from regional / remote areas, ATSI, CaLD in each working group. Proposed changes tend to impact these groups significantly more and their specific barriers and needs should be considered.
  • Participants and family carers need to be involved in the working groups.
  • Can people be on more than one working group?
  • Do the DRCO representatives on the working groups need to be the people who have attended the Post-budget forums so far?
  • Can one person from a DRCO be on one working group and another person be on another group, because that might be more their specialty?
  • Contemplate changing approach it if it’s not working after a set time (adaptively managing).
  • Important that working groups are robust but have flexibility. As we go through this process it may become apparent some people’s interests lie in what other working groups are doing, and so we need the flexibility to change where appropriate.

Page 218 of 390

Alternative co-design approach

Proposed alternative co-design approach:

  • Shared definition of the thing that needs to be done;
  • Round-table/fully-inclusive identification of potential strategies and tactics that can be employed to get the thing done within legislative and fiscal constraints;
  • A genuinely collaborative approach to building the strategies and describing those tactics agreed to (for example, by having Google Docs draft policy documents that have genuine shared authorship); and
  • A commitment to getting approval from all design contributors after the plan to get the thing done is written and not before it.

Objectives

Propose to include an objective that recognises and embeds, intersectionality.

Communication

Hugely important to have a way to connect between working groups where reforms may overlap.

Need a variety of open channels for people to engage.

Engagement framework

Add “verify” to the engagement framework to show it is an iterative process, willing to readdress a strategy/initiative at any phase if identified as not going to have the required impact.

Important that this program of work does not unravel great work done previously in the sector.

DRCO remuneration

DRCOs need to be appropriately funded to participate in this program of work.

Notes the tight labour market currently, and the issue of recruiting staff to support this work.

Resourcing challenge for DRCOs who also have other program of work to participate in, for example, the National Autism and Strategy Review.

Governance model

Steering group and quarterly meeting

  • The proposed working group, steering committee and quarterly meeting concept provides a good starting point for this program of work. Need to ensure we refine the approach as we progress, if required.
  • Important that whatever the working groups develop, that it comes back to the larger group to verify and support.
  • It is important that whatever approach is taken, that it is iterative, and that there is governance in place to ensure there is alignment between the work of the working groups.
  • Important to have robust steering group and quality reporting to ensure the larger group stays across working group work.
  • Need a process for managing and coordinating any overlap between working groups so they do not end up at cross purposes. Suggest some people are on more than one group to help with cross group coordination.
  • Important to have a mechanism that allows for all proposed reforms to be assessed to ensure they will not negatively impact any other proposed reform or identify potential risk and subsequently develop a contingency plan(s).
  • Steering Committee to be responsible for identifying ‘opportunities’ as well as risk.
  • Change proposed governance model to “Integration Steering Committee” (Slide 7 RFO Co-design approach powerpoint).
  • Significant concern if the RFO program quarterly meeting replaced the DRCO Forum. The sector still needs a place to raise issues with the NDIA.

Issue prioritisation

  • Important that the governance model has a mechanism to prioritise reforms between working groups, to ensure the reforms that will have the biggest impact are prioritised.

Alternate governance model

  • Retain the working group model.
  • Modify the process to reflect more work and planning up front in short sprints. Add verification points/ decision gates throughout the rest of the stages. This will help support the following principles:

For Official Use Only

  • Harness co-design from stakeholders at the critical points to ensure that diversity of domain knowledge has been captured. This also allows potentially broader representation.
  • DRCO indicating they are resource strapped - people and time by focussing on the critical points
  • Provides transparency and co-design at the points of most risk and opportunity
  • Enables traction so that outcomes can be achieved in an effective timeframe and allows NDIA to take carriage of detailed development and implementation. Also avoids the trap of trying to agree over protracted periods.

2.3.3. Establish a separate working group that may only be for the initial stages to mobilise – may be the Steering Committee if have the right skills, may be a combination of Steering Committee and those with specialised skills. Main goal of this working party is to develop the process and framework for uniformity.

This includes more than modifying an existing outcomes framework but includes assessment of problem to solve, measures of success, impact initiative will have, likely resources, risks, interrelationships, conflicts, stakeholders etc. The working group can develop the profile of each initiative and provide back to the working group for discussion and progress. This will enable identification of priorities so can identify which initiatives will have the biggest impact in the relevant timeframe. There are techniques to do this at a high level, quickly even with uncertain information. It will also avoid the risk of initiatives unravelling as they conflict. You likely know this so apologies in advance if highlighting anything obvious.

2.3.4. This group to also capture and assess new ideas put forward by DRCOs.

Reform for outcomes program initiatives

General

The outcomes of the Scheme need to be made clearer.

Need clarity around the responsibilities of the different systems. For example, the responsibility of the community mental health service to support an NDIS participant.

The RFO program needs to align with other work being done in the sector, including the:

  • NDIS Review
  • the Disability Royal Commission
  • the National Autism Strategy
  • national regulatory harmonisation
  • the National Gender Equality Strategy
  • review of the Disability Services Act

Extremely important that members have visibility of the previous co-design processes undertaken with learned frameworks & process IP shared with the group.

Will there be mental health-specific approaches?

Where do family member/carers fit into this?

Where does addressing structural barriers to citizenship sit – ie, lots of work on addressing ‘supports’ in participants but nothing addressing systemic burdens – housing, employment, income, relationships, lack of individual advocacy, carceral and otherwise iatragenic health systems etc

NDIA modelling needs to include specific disabilities.

Concern the modelling that has led to the 8% growth target does not account for the growth in the autism population.

The NDIA Outcomes Framework needs to be reviewed and updated. Needs to reflect government’s emphasis on well-being and updates to measurement and reporting

Need to align the NDIA Outcomes Frameworks with:

  • frameworks for integrated support, particularly when a participant is receiving multiple services
  • a core guiding value and / or aspirations. For example, social and emotional wellbeing

NDIS

  • the unique situation of each individual, and their needs, wants and circumstances

3.1.12. The NDIA Outcomes Framework should draw in measures from external frameworks that are aligned to the: * International Classification of Functioning, Disability and Health (ICF) * Social determinants of health, and * wellbeing.

Workforce capability

  • 3.2.1. The NDIA should commit to employing more participants across all positions, not just planners
  • 3.2.2. Can the Workforce capability funding be invested in expanding the number of delegates directly employed by NDIA? Ideally, the majority of people would prefer the planning role of LACs to be phased out entirely so that people meet directly with the decision-maker
  • 3.2.3. Needs to consider the Prime Minister’s draft National Strategy for the Care and Support Economy.
  • 3.2.4. Workforce planning needs to be across the whole Agency to achieve better outcomes.
  • 3.2.5. This working group reform should include driving a reduction in unethical provider practices as a result of changing current NDIS practices. Change here and get reduced fraud.
  • 3.2.6. Won’t the PACE system mean LACs will no longer be needed?

Better planning

  • 3.3.1. Over 2021-22 we saw plan reductions of 20-75% on the majority of plans (average of 40% cuts). The only participants we’ve worked with who have overspent their plans, did so because their funding had been drastically cut.
  • 3.3.2. Will LACs continue to do planning meetings and draft plans long-term, or will this role be transferred to delegates?
  • 3.3.3. Build staff knowledge and expertise in specific disability types and cultures.
  • 3.3.4. Will the planning group address the issue of Planning (NDIA funded plan) and planning (visioning for a good life, learning from peers, choosing who you plan with)?
  • 3.3.5. Planners need to have improved knowledge of disability, for example, Autism, before they take on a planner role.

— Page 223 of 390 —

NDIS

Flexibility

  • Agree that as the NDIS is an insurance-based scheme, there is an expectation that support reduces over time. Need to balance this with ensuring participants receive the support they need, when they need it.

  • Need to clarify what is meant by “exits.” There is a presumption that a range of effective ‘Tier 2’ supports are available to support participants that exit. This is not the case.

Planning

  • Planners should have minimum core competencies, besides lived experience or capability in understanding delivery of best practice approaches.

  • Planning should focus on meeting participant needs. Would like to see goals and planning separated.

  • Planning either needs other preparatory supports behind it to be successful, or planners need more time & skills than we currently allow to do it well (at least for people living with psychosocial challenges and others).

  • Planning should be done by an accredited life planner of the participant’s choice, then the plan is submitted to the NDIA delegate for funding approval.

  • Key performance indicators impact the accuracy and quality of plans, and increasing the volume of S100 and S48 requests.

  • Need to ensure informal carer advice is respected by planners.

  • Need to look at how to build capacity in informal carers.

  • Will the planning group address the issue of planning for NDIA purposes such as a vision for a good life, learning from peers and that kind of thing?

  • Big life’ planning should be done in a way that feeds into the NDIA.

  • There is a risk we will continue to see inconsistencies If LACs, or other external parties, are doing planning in some areas and not others.

  • When LACs are being used to do detailed plans, not the big visioning stuff, then we are getting mixed outcomes.

  • It is important that this process seeks not a consistency of results, because it is a person-centred scheme, but consistency in terms of the resources that make the Scheme work.

  • Need to have resourcing and arrangements in place to ensure any changes made do not negatively impact the NDIS and people with disability.

  • Support coordinators need to understand any changes that are made and how to implement those changes and know how to fix issues participants have.

NDIS

Recommendations and Issues

Section 3.4: Flexibility in Plans for Permanent Disabilities with Fluctuating Needs

3.4.3. Suggest people with permanent disabilities, who have fluctuating needs, can remain in the Scheme, but opt to have a $0 plan until their needs increase. The NDIA would need to publicise this option. This could mitigate people’s fear of not being able to regain access if their needs increase.

3.4.4. The increasing number of plan rollovers and auto-extensions creates an issue with the ‘About Me’ section of participant plans (and also with how goals are implemented). The information changes and isn’t updated. As part of the PACE rollout, is it possible to enable participants to update the ‘About Me’ section of their plans in the portal? As participants are being expected to comply with their plans, it causes problems when the info in the plan is no longer correct.

3.4.5. People with disability should always be able to access the supports they need to live an ordinary life.

3.4.6. Need a clear definition of ‘early intervention’ and what conditions need to be met to count as ‘early intervention’.

Section 3.5: Independent Living

3.5.1. When the NDIS was being designed my organisation recommended that the NDIA have in place long term contracts with DROs as expert providers of information on demand to staff and contracted coordinators, in addition to liaison and co-design roles. This idea could be revisited.

3.5.2. SIL is a major concern which has been raised with Rebecca and Corri at recent meeting, why are planners getting the costing so wrong?

3.5.3. Make sure participants at risk of overusing their plan are identified and supported early.

3.5.4. Need to change the acronym SIL. It contains assumption about independence. Suggest Assistance with Home and Living (AHL).

3.5.5. How will the work on the independent living initiative align with:

  • the supported decision making policy?
  • planning decisions, because we need to prioritise the decisions people make themselves around their home and living options.

Section 3.6: Evidence-based Supports

3.6.1. Need to agree what

NDIS

For Official Use Only

  • 3.6.4. What constitutes evidence? Will participant input be considered evidence.
  • 3.6.5. Is the intent that the Evidence Based Supports working group would look at Market Stewardship and what a good provider looks like? Or is that part of DSS and the commission?
  • 3.6.6. Need to help people select policy providers. Need to address what is meant by a quality provider
  • 3.6.7. There are certain practices that help facilitate fraud and bad practices. Need to work out whether it sits under the Evidence Based Supports initiative or under the Fraud initiative or Workforce Capability initiative.

3.7. Fraud

  • 3.7.1. There is a conflict of interest when a provider can undertake an assessment of disability and also be a provider of services. This needs to be changed. NB this is not fraud because the NDIA allows it.
  • 3.7.2. Will participants be targeted for compliance, or will the focus be primarily on providers? Will participants incur debts and have Centrelink payments deducted to repay debts, for example, for expenditure that is 5 years old?
  • 3.7.3. Need to ensure appropriate safeguarding and protections are in place to protect participants from coercion from a provider or family member perpetuating fraud.
  • 3.7.4. This working group needs to drive change in reducing unethical provider practice by changing current NDIS practices, unless this change is the responsibility of the Evidence Based Supports working group.
  • 3.7.5. As part of the work around Fraud, there needs to be capacity building work to support decision making. So there is overlap between the Fraud initiative and the Workforce Capability initiative.

.

— Page 226 of 390 —

Working Groups preferences

  • Top 3 preferences listed, unless stakeholder stated they wish to work in all working groups.
    • NB: Sylvana Mahmic said ‘Use me if and where you feel it’s helpful’.
    • Chair nominations highlighted.
Working group Workforce capability Better Planning Flexibility Independent living Evidence-based supports Fraud
Representative nominations Bob Buckley, A4
Sally Karandrews, BCA
Alison Brook, CA
Skye Kakoschke-Moore, CYDA
Bill Gye, CMHA
Jen Blyth, DA
Darryl Steff, DSA
Catherine McAlpine, IA
Melanie Keeley, SARU
Sylvana Mahmic, IAC
Jenny Karavolos, AAA
James Manders, IAC
Carolyn Hodge, PWDA
Nick Avery, EAC
Bronwyn Morkham, YPINH
Robbi Williams, JFA
Eileen McDonald, NMHCCF
Bob Buckley, A4
Sally Karandrews, BCA
Alison Brook, CA
Skye Kakoschke-Moore, CYDA
Jen Blyth, DA
Jeff Smith, DANA
Darryl Steff, DSA
Catherine McAlpine, IA
Carolyn Hodge, PWDA
Simon Burchill, PDA
Dr George Taleporos, IAC
Bob Buckley, A4
Alison Brook, CA
Skye Kakoschke-Moore, CYDA
Jen Blyth, DA
Jeff Smith, DANA
Dwayne Cranfield, NEDA
Carolyn Hodge, PWDA
Dr George Taleporos, IAC
Bob Buckley, A4
Jeff Smith, DANA
Darryl Steff, DSA
Catherine McAlpine, IA
Dwayne Cranfield, NEDA
Dr George Taleporos, IAC
Bob Buckley, A4
Sally Karandrews, BCA
Bill Gye, CMHA
Simon Burchill, PDA
Melanie Keeley, SARU
Sylvana Mahmic, IAC
Jenny Karavolos, AAA
Nick Avery, EAC
Bob Buckley, A4
Dwayne Cranfield, NEDA
Simon Burchill, PDA
Sylvana Mahmic, IAC
Jenny Karavolos, AAA
  • if only place to address changing NDIS practices reduce unethical practice Nick Avery, EAC |

Working Groups preferences

  • Top 6 preference list.
  • Chair nominations stated.
Name / Organisation Workforce capability Better Planning Flexibility Independent living Evidence-based supports Fraud
Bob Buckley, Autism Aspergers Advocacy Australia (A4) All All All All All All
Jenny, Karavolos, Australian Autism Alliance 3 and Chair 6 4 and Chair 5 2 and Chair 1 and Chair (This is my number 1 if this is the only place to drive change in reducing unethical practice of providers)
Katherine Annear, Autistic Self Advocacy Network of Australia and New Zealand (ASAN AUNZ)
Ross Joyce, Australian

Page 228 of 390

| Federation of | Disability | Organisations | | Sally Karandrews, Blind Citizens Australia | 1 | 3 | 2 | | Nick Rushworth, Brain Injury Australia | | | | | | Alison Brook, Carers Australia | 1 | 2 | 3 | | Skye Kakoschke-Moore, Children and Young People with Disability Australia (CYDA) | 3 | 1 and Chair | 2 | 6 | 4 | 5 | | Bill Gye, Community Mental Health Australia (CMHA) | 1 | | | | 2 | | Jen Blyth, Deaf Australia | 1 | 3 | 2 | | David Murray, Deafblind Australia | | | | | |

Steve Williamson, Deafness Forum of Australia
Jeff Smith, Disability Advocacy Network Australia (DANA) 5 1 and Chair 3 2 4
Darryl Steff, Down Syndrome Australia 2 and Chair 1 and Chair 4 3 6
Nick Avery, Every Australian Counts 4 1 3 5 2
Damian Griffis, First Peoples Disability Network
Catherine McAlpine, Inclusion Australia 3 2 4 1 and Chair 5
Robbi Williams, JFA Purple Orange 1 2 3
Carolyn Nikoloski, Mental Health Australia
Eileen McDonald, National Mental 2 and Chair 1 and Chair 3 and Chair 4 and Chair 5 and Chair

| Health Consumer Carer Forum | — | — | — | — | — | | Dwayne Cranfield, National Ethnic Disability Alliance | 2 | 1 | 3 | | Carolyn Hodge, People with a Disability Australia | 1 | 3 | 2 | 4 | 5 | 6 | | Simon Burchill, Physical Disability Australia | 1 | | | 2 | 3 | | Yvonne Keane, ReImagine Australia | | | | | | | Melanie Keeley, Self-Advocacy Resource Unit (SARU) | 1 | | | | 2 | | Carolyn Frohmader, Women with Disabilities Australia | | | | | | | Bronwyn Morkham, Young People in | 2 | 1 | 3 | 4 | 6 | 5 |

Nursing Homes

National Alliance

Sylvana Mahmic, IAC Member | Any | Any | Any | Any | Any | Any James Manders, IAC Member | 3 and Chair | 2 | 1 | Dr George Taleporos, IAC Member | 4 | 2 and Chair | 1 and Chair | 3 and Chair | 6 | 5 Leah van Poppel, IAC Principal Member | Dr Sharon Boyce, IAC Member | Jennifer Cullen, IAC Member | Dr Leighton Jay, IAC Member |

Tricia Malowney, IAC Member
Sam Paior, IAC Member
Mark Tonga, IAC Member
Liz Reid, IAC Member
Gavin Burner, Intellectual Disability Reference Group Member (attends all Council meetings)
Comments

Loading comments…

What kind of comment is this?
Add a comment