Add assistive technology capacity building supports in a plan

‹ PrevPage 1 of 4 · Source p. 45Next ›

Add assistive technology capacity building supports in a plan

The content of this document is OFFICIAL. This Standard Operating Procedure (SOP) will support you to add funding for capacity building Low Cost, Mid Cost and High Cost assistive technology (AT) supports.

Recent updates

Date What’s changed
September 2020 1. New SOP format to align with Operational Guidelines refresh. SOPs include process information only. Use Operational Guidelines to help you make decisions and refer to Related procedures or resources.
2. You must include a minimum of $500.00 ($700.00 for participant’s living in remote or very remote areas) of Capacity Building support for Low Cost AT supports.

Checklist

Topic Checklist
Pre-requisites - You have read and understood Operational Guidelines – Assistive Technology.
- You have determined the reasonable and necessary funding needed to assess, find and set up all of the participant’s AT supports.
- You have received TAB advice, if needed.
- You have determined what AT is reasonable and necessary.
- You have included funding for AT supports.
- You have used the Practice Guide - Hearing Supports to determine Capacity Building supports for participants with hearing loss.
Actions - 3.1 Add Capacity Building supports
- 3.2 Next steps

Standard Operating Procedure

OFFICIAL For internal use only

Procedure

Add Capacity Building supports

  1. In Planning – Staff Tasks, select the Determine the Funded Supports task.
  2. The Determine the Support Needs form will open. Select Capacity Building.

[Image not converted to Markdown – “Image of the Determine the Support Needs form” – check the source PDF page for the actual content]

  1. The two capacity building sub-types appear. Select Capacity Building.

[Image not converted to Markdown – “Image of the Support Category section with Capacity Building selected” – check the source PDF page for the actual content]

V3.0 2020-12-07 Assistive technology - Capacity building supports Page 2 of 4 OFFICIAL This document is uncontrolled when printed. Page 46 of 875

Standard Operating Procedure

OFFICIAL For internal use only

  1. Include funding in CB Daily Activity at budget level to assess, source and set up all of the participant’s AT supports. The amount of reasonable and necessary capacity building supports will be different for each participant. As a minimum, you need to include $500.00 or $700.00 for participant’s living in remote or very remote areas.

Note: To include funding at budget level you increase the amount of funding in the CB Daily Activity Price field (highlighted below) by the amount of funding. This means that you do not use support items to add funding.

Support Type Support Category Capacity Building
Support Category Price $ Comment
CB Choice & Control 0.00
CB Daily Activity 0.00
  1. In the Comment section include the following: Support from an AT assessor to assist me to select, set up and use my assistive technology.
Support Type Support Category Capacity Building
Support Category Price $ Comment
CB Choice & Control 0.00
CB Daily Activity 1,165.00 Support from an AT assessor to assist me to select, set up and use my assistive technology

Next steps

  1. Check you have included all other reasonable and necessary supports when completing the Determine the Funded Supports task. Refer to relevant planning resources when completing the remaining steps to develop the participant’s plan. V3.0 2020-12-07 Assistive technology - Capacity building supports Page 3 of 4 OFFICIAL This document is uncontrolled when printed. Page 47 of 875

Standard Operating Procedure

OFFICIAL For internal use only

  • Operational Guidelines – Assistive Technology
  • Planning resources Intranet page

Feedback

If you have any feedback about this Standard Operating Procedure, please complete our Feedback form.

Version control

Version Amended by Brief Description of Change Status Date
2.0 BIB217 Class 3 approval.
Standard Operating Procedure moved to the new SOP format to be used with the Assistive technology operational guidelines. APPROVED 2020-10-07
3.0 CW0032 Class 1 approved.
Updated links to assistive technology guidance. APPROVED 2020-12-07

V3.0 2020-12-07 Assistive technology - Capacity building supports Page 4 of 4 OFFICIAL This document is uncontrolled when printed. Page 48 of 875