National Disability Insurance Agency Risk Management Strategy

‹ PrevPage 1 of 14 · Source p. 1Next ›

National Disability Insurance Agency

Risk Management Strategy

September 2015

Page 1 of 14

Contents

Risk Management Strategy ……………………………………………………………………………………………………… 3 Risk Context ………………………………………………………………………………………………………………………. 3 Risk Governance…………………………………………………………………………………………………………………. 4 The Risk Management Process …………………………………………………………………………………………….. 7 Risk Management Reporting Responsibilities ………………………………………………………………………. 11 Communication and Culture ………………………………………………………………………………………………. 13 Risk Management Function ……………………………………………………………………………………………….. 13 Compliance ……………………………………………………………………………………………………………………… 14 Review of the Framework ………………………………………………………………………………………………….. 14


Page 2 of 14

Risk Management Strategy

Risk Context Consistent with the responsibilities of a Board as articulated in CPS 220, and in accordance with section 8 of the NDIS Risk Management Rules, the Board formulates a Risk Management strategy for the Agency.

The Board’s approach is to ensure that risk management is integral to the way the Agency conducts its business. In this way, the Board seeks to ensure that the benefits of a structured approach to risk management are realised.

The Board develops the NDIS Strategic Plan (with a three year horizon), identifies key risks to achieving the objectives of the Strategic Plan (the Strategic Risks), and then articulates its attitude towards the management of them through the Risk Tolerance Statement.

Of particular importance is ensuring that risks to the achievement of the Board’s strategic objectives are adequately addressed through the Agency’s business planning processes.

Identifying risk during the business planning process allows the Board to set realistic delivery timelines for strategies and activities, or to choose to remove a strategy or activity if the associated risks are too high or unmanageable.

The Agency Corporate Plan, approved by the Board, sets out annual Agency-wide priorities for action that give effect to the objectives of the Strategic Plan, including priorities for the management of the Strategic Risks.

Responsibility for managing each Strategic Risk is allocated to members of the Executive (CEO, Deputy CEOs and General Managers) in the Agency Corporate Plan. Cascading from the Agency Corporate Plan are Divisional and Branch/ Site Business Plans, and, where appropriate, Section Business Plans. Each of these plans also has a twelve month horizon.

In their Divisional Business Plans, General Managers identify, and outline management strategies for, operational risks that sit below each Strategic Risk. Operational risks are, essentially, the risks to “business as usual” deliverables that contribute to the achievement of strategic objectives.

Additionally, the Board has identified a number of projects of strategic significance – projects where additional, time-limited effort is needed to ensure the achievements of objectives. These projects are monitored by the Board separately from regular management performance reports.

Risks to the successful delivery of projects are assessed and treated as part of the project risk management process, with accountability vested at the General Manager level.

Although individual members of the Executive manage strategic, operational and project risks, information about the risks, existing controls, mitigation strategies, and progress with implementing any remedial actions is collated centrally by the Chief Risk Officer. Regular reports are provided to the Audit, Risk and Finance Committee and to the Board.

                          Page 3 of 14

Risk Governance

The Board is ultimately responsible for ensuring efficient and effective risk management in the Agency.

The Board fulfils its responsibilities for managing risk with advice from the Audit, Risk and Finance Committee, which is responsible for monitoring the risk management process and providing independent assurance and assistance on risk management to the Board.

The Sustainability Committee pays particular attention to the management of risks around financial sustainability including the achievement of outcomes by participants.

In addition, a specialist ICT Committee has been established to oversee delivery and management of risks associated with development of a fit-for-purpose ICT system during the Scheme roll-out phase. Recognising the importance of managing prudential risk, the Audit, Risk and Finance Committee and the Sustainability Committee work closely to ensure risks identified by the Scheme Actuary are integrated into broader Agency-wide risk management mechanisms.

The NDIS Act and Rules emphasises the Scheme Actuary’s role in assessing the financial sustainability of the scheme and advising the Agency and Board of any risks to financial sustainability. Specifically under Section 180B of the NDIS Act and Rules, the Scheme Actuary in an annual report must:

  • Assess the financial sustainability of the Scheme.
  • Assess risks to that sustainability, consider the causes of any risks, and discuss recommendations to manage or address these risks.
  • Include in an annual financial sustainability report a discussion of the Agency’s risk management arrangements (all systems, structures, cultures, processes, policies and people that identify, assess, mitigate and monitor all sources of risk, both internal and external to financial sustainability) and any recommendations in relation to any inadequacies.

The Scheme Actuary has broad oversight of all risks identified and the processes for mitigating these risks through involvement in the following committees:

  • Operational Policy Committee (a Management committee which reviews reports on operational risks, and identifies new and emerging operational risks);
  • Executive Management Group ( which reviews reports on strategic risks and identifies new and emerging strategic risks);
  • ICT Committee (sub-committee of the Board);
  • Audit, Risk and Finance Committee (sub-committee of the Board); and
  • Sustainability Committee (sub-committee of the Board). The Chief Executive Officer (CEO) has overall responsibility for how risks are managed by the Agency.

The CEO and Executive Management Group (EMG) meet quarterly to monitor risks to the achievement of the Agency’s strategic plan and the management of strategic risks identified by the Board.

In line with the three lines-of-defence risk governance model identified by APRA in CPS 220, the CEO and Executive Management Group are responsible for ensuring that risk ownership is clearly defined and that the risk management framework is effectively implemented and supports decision-making. Managers at all levels – risk owners - are responsible for satisfying themselves that the key risks relating to their area of business are being managed appropriately and that they can provide assurance of this where required.

The governance framework enables the management of risk to be integrated into all key business functions, processes, systems, programs and projects. It also provides a sound foundation for the

Table 1: Risk Management Roles and Responsibilities

Board and EMG to make informed decisions which assure that proper controls are in place and that risks are well managed.

Key roles and responsibilities for staff at all levels in the Agency, as well as Board members, are summarised in Table 1 below.

Position Roles and Responsibilities
NDIA Board The Board approves the overall risk strategy, and determines its appetite and tolerance for risk. It receives strategic risk reports quarterly and directly monitors the treatment of any risk that falls outside risk tolerances (as communicated in the risk tolerance statement).

At the end of each financial year of the Agency’s operations, the Board provides the COAG Disability Reform Council with a risk management declaration signed by at least two Board members on behalf of the Board. | | Audit, Risk and Finance Committee | The Audit, Risk and Finance Committee oversees the development and implementation of the risk management strategy and the tools and templates to assist staff to implement and practice risk management. On an ongoing basis the Committee provides assurance to the Board, independent of management, on the effectiveness and efficiency of the Agency’s risk management strategy and framework, the identification and management of risks and advises on whether the internal audit plan is ‘risk informed’. The Audit, Risk and Finance Committee also notifies the Board of any significant breach of, or material deviation from, the risk management strategy or framework | | Sustainability Committee | The Sustainability Committee is responsible for monitoring and reporting to the Board on the sustainability of the Scheme and whether Scheme objectives are being met. It does this through monitoring eligibility and access to the Scheme by participants, increases in the cost of reasonable and necessary support and achievement by participants of their individual goals. It also provides advice to the Board on potential changes to the legislation or other regulation. | | ICT Committee | The ICT Committee is responsible for monitoring the development and delivery of a fit-for-purpose ICT system, for the roll-out phase of the Scheme. It also advises the Board on risks and inter-dependencies of the programme. | | Scheme Actuary | The NDIS legislation emphasises the Scheme Actuary’s role in assessing the financial sustainability of the Scheme and advising the Board of any risks to financial sustainability. In carrying out this responsibility, the Scheme Actuary works closely with the Sustainability Committee. Risks identified by the Scheme Actuary, either to financial sustainability or to the achievement of participant outcomes, are fed into the Agency’s risk management process. | | Chief Executive Officer (CEO) | The CEO has ultimate accountability and overall responsibility for the Agency’s performance, including the accountability for management of risk in the delivery of the Scheme’s outcomes. | | General Managers | General Managers are responsible for identifying, documenting, prioritising, monitoring and treating all material risks in their divisions. Executives will implement the risk management strategy and framework, promote and encourage the use of risk management tools and processes in their divisions, ensure risk management plans are regularly reviewed and updated, and monitor risks. |

Page 5 of 14

Roles and Responsibilities

Risk Owners Risk owners — usually General, Branch or Site Managers — are responsible for the implementation and ongoing maintenance of the risk management framework, including the identification and effective management/mitigation of risks, and issues identification, recording, escalation and management.

Chief Risk Officer (CRO) The Chief Risk Officer assists the Board and senior management by providing independent and objective review and challenge, oversight, monitoring and reporting in relation to risk to the Agency’s business operations. The CRO works with other managers to establish effective risk management in their areas of responsibility. The CRO has independent access to the Audit, Risk and Finance Committee and has the resources to help effect appropriate enterprise risk management across divisions, functions, and activities. The CRO has responsibility for monitoring progress and for assisting other managers in reporting relevant risk information up, down, and across the NDIA.

Executive Management Group (EMG) EMG will meet at least once a quarter to monitor risks to the achievement of the Agency’s corporate plan and goals, and the management of strategic risks identified by the Board. It will report quarterly to the Audit, Risk and Finance Committee.

Agency Operational Policy Committee The Operational Policy Committee is a Management committee supporting EMG within the Agency. This Committee will have primary responsibility for Agency- wide operational risk management.

Divisional/ Site Risk Officers (Risk Champions) Each General Manager and Site Manager will nominate an individual to co- ordinate risk management activities within that organisational unit. Division/ Site Risk Officers will act as ‘risk champions’ by promoting awareness and assistance with the delivery of risk management activities; assist with the identification, assessment, mitigation and monthly tracking of risks across the Division/ Site; and report to General/ Site Managers on the status of risk issues.

All Staff All staff carry the responsibility for the identification and management of risks that impact on their work areas. All staff should recognise, communicate and respond to expected, emerging or changing risks and contribute to the development and implementation of risk treatments.

In practice, this means that staff:

  • must be familiar with the Agency’s risk management strategy and policy;
  • are encouraged to alert their managers to the presence of risks and participate in their management; and
  • are encouraged to make use of the tools available to them so that they are better able to identify and manage risks in the workplace.

The Risk Management Process

The processes used for managing risk in the Agency are closely aligned with the Australia/New Zealand Standard on Risk Management (AS/NZS ISO 31000:2009). This involves seven key steps:

  • Step 1 - Communicate and consult;
  • Step 2 - Establish the context;
  • Step 3 - Identify risks;
  • Step 4 - Analyse risks;
  • Step 5 - Evaluate risks;
  • Step 6 - Treat risks; and
  • Step 7 - Monitor and review.

The linkages between each step in the process are set out in Figure 1 below.

Figure 1: The NDIA’s Risk Management Process

Communicate and consult

Risk context Risk identification Risk analysis Risk evaluation Risk treatment
*Review controls *Assess consequence *Assess likelihood Determine current risk level Evaluate risks Rank risks *Risk acceptance (yes/no) Determine target risk level

Monitor and review

Following this process at all levels of risk management — strategic, operational or project — ensures that the Agency’s approach to risk management is both comprehensive and consistent.

Step One — Communicate and Consult

Communication and consultation with internal and external stakeholders is important through all stages of the risk management process to ensure the Agency has a comprehensive picture of risks in its operating environment.

External communication and consultation is targeted at informing external stakeholders of the Agency’s risk management approach; the effectiveness of that approach; and requesting feedback where appropriate. It is mainly directed at the level of the strategic risks, and as such, is primarily the responsibility of the Board and the EMG. In the case of consultation with Governments, through the CDRC, the Chair of the Board and the CEO have major carriage.

As part of its commitments to transparency and inclusiveness, the Board also seeks comment and engagement from participants and other interested stakeholders through the Scheme website.

Engagement with stakeholder governments and people with disabilities are critical for Scheme success.

Internal communication and consultation is aimed at informing internal stakeholders of the key strategic risks and their responsibilities relating to the management of these risks, as well as seeking their contribution to the identification and mitigation of operational risks. It is mainly facilitated by

Divisional and Branch/ Site Managers supported by the Agency Operational Policy Committee and the Chief Risk Officer.

Step Two – Establish the Context

This involves stating the objectives of the Agency up front, as clearly as possible, in order to identify risk areas precisely, and consider their potential impact on Scheme outcomes. It means considering:

The external context

Building an understanding of external stakeholders, and the extent to which the external environment will impact on the ability to achieve corporate objectives, by considering the business, social, regulatory, cultural, competitive, financial and political environments in which the Agency operates; and the Agency’s strengths, weaknesses, opportunities and threats.

The internal context

Building an understanding of organisational elements and the way they interact, including governance, organisational structure, roles and accountabilities; policies, objectives, and the strategies that are in place to achieve them; capabilities (people, time, systems, processes, technologies and capital); the relationships with and perceptions and values of internal stakeholders; the organisation’s culture; information systems, information flows and decision making processes (formal and informal); standards, guidelines and models adopted by the Agency; and the form and extent of contractual relationships.

By paying attention to these and other relevant factors, the Agency can ensure that the risk management approach adopted is appropriate to the circumstances, and is supported by an appropriate level of resourcing.

Step Three – Identify Risks

This step involves reviewing as many sources of risk as possible, to identify the risks that could impact on the achievement of the Agency’s objectives. Because unidentified risks can always pose a major threat, it is important to take care to ensure that the Agency maintains an open perspective on all possible threats and opportunities.

Key information sources to consider include the NDIA Strategic, Corporate and Business Plans; internal and external audit reports; post-event or post-implementation reviews; and local and overseas experience. Risks can be identified using various tools and techniques, some of which have been condensed into templates to assist in the risk identification process.

By considering these, the aim is to identify a comprehensive list of risks that could adversely impact the achievement of Agency objectives, as well as risks associated with not pursuing opportunities that could foster the achievement of objectives.

Step Four – Analyse Risks

Once a risk is identified, it is important to describe it adequately. A comprehensive risk analysis will include consideration not only of a particular risk event, but also of its causes and consequences.

Risk analysis involves identifying the likelihood of the risk occurring, identifying the potential consequence or impact that would result if the risk was to occur; identifying the controls currently in place to manage those risks by reducing either the consequence of the risk, or its likelihood; and assessing the effectiveness of current controls.

Controls are aimed at bringing the risk within an acceptable level. When evaluating the effectiveness of current controls, the factors to consider include consistency of application, understanding of control content; and documentation of controls (where appropriate).

Risks are then analysed and rated after consideration of current controls, in accordance with a standard risk matrix, approved by the Board.

FOI 20/21-0881

Step Five – Evaluate Risks

The risk evaluation stage involves using the results of the risk analysis to determine whether additional actions need to be taken to manage risks, and the priorities for treatment implementation.

This involves determining whether the risk, with the current level of controls, is acceptable or unacceptable to the Agency in accordance with the Board’s approved risk tolerance statement.

Step Six – Treat Risks Treatment actions are required where the current controls are not managing the risk within acceptable tolerance levels. There are a number of ways of treating risk:

  • Avoid the risk – change a business process or objective so as to avoid the risk, or decide not to start or continue with the activity that gives rise to the risk;
  • Remove the risk source;
  • Change the likelihood – undertake actions aimed at reducing the cause of the risk;
  • Change the consequence – undertake actions aimed at reducing the impact of the risk;
  • Share/transfer the risk – transfer ownership and liability to a third party, for example, through a contractual arrangement;
  • Retain the risk – accept the impact of the risk; and
  • Increasing the risk in order to pursue an opportunity.

When determining the preferred treatment option, consideration is given to the cost compared to the likely benefits that will be derived, including the risk reduction that will result, but also considering legal, regulatory and other requirements such as social responsibility and the social contract between the Agency and Scheme participants. Decisions also take into account risks which can warrant treatment other than on economic grounds, such as risks to the Agency’s reputation, or levels of public confidence in the integrity of the Scheme. Once the preferred treatment option has been selected, the cost of any actions is incorporated into the relevant budget planning process; a responsible person is designated for delivery of the action, and performance measures are determined. The preferred option is documented in a risk treatment plan that sets out how the chosen risk treatment will be implemented. Treatment plans include the reasons for selection of treatment options, including expected benefits to be gained; those who are accountable for approving the plan and those responsible for its implementation; proposed actions; resource requirements including contingencies; performance measures and constraints; reporting and monitoring requirements; and timing and scheduling. Risk treatment plans are also incorporated into other Agency processes, such as business or project management plans. Risk treatment involves a cyclical process of assessing the treatment; deciding whether residual risk levels are tolerable; if not, generating a new risk treatment; and assessing the effectiveness of that treatment. This has been built into the risk reporting process used in the Agency, and so occurs at intervals determined by the nature of the risk and the priority accorded it by the Board or senior management.

                          Page 9 of 14

Step Seven – Monitor and Review

The Agency’s risk monitoring and review processes are aimed at ensuring that controls are effective and efficient in both design and operation; obtaining further information to improve risk assessment; analysing and learning lessons from events (including near misses), changes, trends, successes and failures; detecting changes in the external and internal context, including changes to risk criteria and the risk itself, which can require revision of risk treatments and priorities; and identifying emerging risks.

Risks are monitored and reported at a strategic, operational and project level, as shown in Figure 2 below.

Figure 2: Risk monitoring and reporting

Key elements of the risk monitoring and review arrangements include:

  • Strategic risks are identified and assessed by the Board annually and reviewed by the EMG and Audit, Risk and Finance Committee quarterly

    • The management of particular risks, identified by the Board, may be reported more frequently to the Board if appropriate;
  • Operational risks are reviewed annually as part of the business planning cycle, and management of them is reviewed bi-monthly by General Managers, with High risks reported to the Agency Risk Committee and escalated to the EMG and Audit, Risk and Finance Committee as required;

  • Targeted risk assessment of specialist risks including compliance, business continuity, workplace health and safety and fraud are undertaken in accordance with legislative requirements; and

  • Project risk assessments are undertaken for significant projects and monitored monthly through the project governance arrangements.

                            Page 10 of 14

Risk Reporting

Reporting is a key element of the “monitor and review” phase of the risk management process. The Agency’s risk management reporting is designed to support a formalised, structured and comprehensive approach to the monitoring and review of its risks.

Risk Management Reporting Responsibilities

Key risk management reporting responsibilities are set out in Table 2 below.

Table 2: Risk Management Reporting Responsibilities

Role Responsibilities
Board Review reports
Communicate to Agency management priorities and issues raised from consideration of risk information reports
Identify new and emerging risks
Audit, Risk and Finance Committee Review reports
Communicate risk information issues to Agency management
Communicate key risk issues to the Board
Identify new and emerging risks
Sustainability Committee Communicate key risk issues concerning sustainability and participant outcomes to the Audit, Risk and Finance Committee and the Board
CEO Review reports
Closely monitor high risks
Identify new and emerging risks
EMG Review reports
Communicate key strategic risk issues and high rated operational risks to the Audit, Risk and Finance Committee
Identify new and emerging risks
General Managers Review reports
Communicate key strategic risk issues to the EMG
Identify new and emerging risks
Agency Risk Committee Review reports on operational and key technical risks
Communicate key operational risk issues to the EMG
Identify new and emerging risks
Risk Owners (Strategic, Operational and Project) Monitor and review the risks which they own
Prepare reports for the risks which they own
Provide the Chief Risk Officer with information on the risks which they own
Identify new and emerging risks
Chief Risk Officer Prepare reports for the Audit, Risk and Finance Committee
Provide guidance to risk owners on the management of their risks
Prepare the suite of reports set out in Table 3 below
Maintain organisational risk registers
Identify new and emerging risks
Management and staff Monitor and review risks within their areas
Identify new and emerging risks
Consult with Line Managers and CRO on risks as appropriate

Page 11 of 14

Risk Escalation

Risk escalation is essential to ensuring that risks are known and understood by the people with the authority to manage them appropriately in the Agency. If the risk is potentially high and requires allocation of substantial risk treatment resources, then it is managed at the Division/ Site level. The Board has overall accountability for managing risks and therefore, where a risk poses a high threat, the Board is informed immediately, through the Chair of the Board in urgent cases or the Chair of the Audit, Risk and Finance Committee in other cases.

Because previously unidentified risks can become apparent at any time during the year, everyone has the ability to identify new and emerging risks.

When a staff member identifies a new or emerging risk, they are required to raise the matter with their immediate supervisor/manager, and to work with them to undertake a risk assessment. Initial escalation should be to the Branch or Site Manager where a preliminary judgement can be made about the severity of the risk.

Branch and Site Managers review the risk information provided and, as appropriate, institute treatment action or escalate it to their General Manager and the Chief Risk Officer. The General Manager and the Chief Risk Officer consider the information provided and escalate as necessary.

If the risk has implications across more than one Branch or Site, the General Manager and Chief Risk Officer consult with other General Managers, as appropriate, before raising the matter with the DCEOs and CEO.

Risk Reports and Recipients

The Chief Risk Officer co-ordinates the preparation of a suite of reports on risk management across the Agency, based on input from accountable managers. The reporting regime, including target audience and frequency, is set out in Table 3 below.

Table 3: Report Recipients and Frequency

Audience Report Frequency
Board, ARFC and EMG Strategic Risk Report, including * Strategic risk profile * Strategic risk treatment status summary * Strategic risk treatment status details * KRl report Quarterly
Agency Risk Committee Operational Risk Report, including * Operational risk profile * Operational risk treatment status summary * Operational risk treatment status details Risk Management Implementation Update Bi-monthly
Agency Project Committees Project Risk Reports (as required) Monthly

Review and Approval

The scope, content and schedule of reports are reviewed annually by the Board Audit, Risk and Finance Committee.

Access to Risk Management Reporting Framework

The Chief Risk Officer and the Risk and Assurance Team maintain all reports and risk registers.

Communication and Culture

There are three key elements in the Board’s approach to ensuring the development of a healthy risk management culture across the Agency.

First, responsibilities and accountabilities for risk management are clearly delineated. The allocation to senior executive managers of responsibility for managing strategic, operational and project risks reinforces the priority given by the Board and the CEO to ensuring effective risk management aligned to the achievement of strategic goals. Senior managers are encouraged to engage with the CRO in developing strategies to mitigate risk.

Secondly, training is provided to all staff, tailored to roles and responsibilities. For example, general risk management and awareness training is provided by the Agency as part of the general onboarding program. This covers basic concepts and principles; an outline of the key components of the Risk Management Framework; and a discussion of the responsibilities of all staff in relation to risk management. A set of templates to guide staff through key steps in the risk management process is available on the staff intranet.

A network of Risk Management Champions, representing all organisational units in the Agency, meets regularly. Training that is more technical is provided to this group as required. An important part of the role of the Risk Management Champions is to raise awareness and provide advice on risk management issues to other staff in their particular work units.

Thirdly, implementation of the risk management process described previously ensures that risk management is a key element of planning and risks are identified, monitored and managed in a consistent and coordinated way.

Risk Management Function

The Agency’s Chief Risk Officer (CRO) is responsible for assisting the Board, committees of the Board and the senior management of the Agency to develop and maintain the Risk Management Strategy and Framework. The CRO is operationally independent, meaning that the position has no direct involvement in the Agency’s functions in relation to the funding or provision of supports under the Scheme. The CRO is able to brief the Board, committees of the Board and senior management of the Agency as necessary, and has access to all aspects of the Scheme that have the potential to generate material risk, including information technology systems and system development resources. The CRO is tasked with notifying the Board of any significant breach of, or material deviation from, the Risk Management Framework in a timely and effective manner.

The CRO fits within the second line of defence outlined in APRA’s Prudential Practice Guide on Risk Management, and has independent oversight of the risk profile and risk management framework, including providing an effective challenge to activities and decisions that materially affect the risk profile. The CRO is supported by the Risk and Assurance Team with responsibilities relating to the co-ordination of risk management operations and activities that support development of an appropriate risk management culture; fraud control, prevention and detection; business continuity planning; corporate planning; and co-ordination of the internal audit function.

The internal audit program is developed in consultation with management and the Board, and approved by the Audit, Risk and Finance Committee. It is a three year program, but reviewed annually to ensure that it continues to reflect current priorities. The Audit, Risk and Finance Committee receives reports on progress with addressing audit findings.

The delivery of the internal audit program is outsourced to a specialist provider. The managing partner for the contract attends all meetings of the Audit, Risk and Finance Committee, and provides an independent report on progress with delivery of the program. The managing partner also has direct and unfettered access to the Chair of the Audit, Risk and Finance Committee and to the CRO.

                          Page 13 of 14

Compliance

The Agency’s compliance obligations can be divided into four categories: the responsibilities of Directors; administration of the Scheme, including the enabling legislation (NDIS Act 2013 and subordinate rules), and requirements under the Intergovernmental and bilateral agreements; specific responsibilities for Commonwealth authorities under the Public Governance Accountability and Performance Act 2013; and general regulatory compliance with relevant Commonwealth legislation. An annual compliance programme has been established covering all areas with results presented to the Audit, Risk and Finance Committee.

Review of the Framework

To assist in formulating its annual risk management declaration, the Board has included a review of the risk management framework, and its operation, in the annual internal audit program. The results of this review are considered by the Board’s Audit, Risk and Finance Committee. Additionally, every three years, the Board commissions a comprehensive review of the appropriateness, effectiveness and adequacy of its risk management framework from an independent and suitably qualified party. This review will cover the extent of any change in the Agency’s operations, the Board’s risk tolerance, and any changes to the external environment in which the Agency operates. This review will assess whether the framework is implemented and effective; remains appropriate for the Agency, taking into account the Board’s current business plan; remains consistent with the Board’s risk tolerance; is supported by adequate resources; and the risk management strategy accurately documents the key elements of the risk management framework that give effect to the Board’s strategy for managing risk. The Scheme Actuary will have the opportunity to contribute to the annual and triennial reviews, and to comment on the outcomes and proposed remedial actions, if any.